Setting Process
- 
								 01 01Structural line and level check 
- 
								 02 02Installation of I/C and wall panels 
- 
								 03 03Installation of beam and SC panels 
- 
								 04 04Installation of staircase panels 
- 
								 05 05Installation of slab panels 
- 
								 06 06Installation of slab panels 
- 
								 07 07Installation of electrical, plumbing components and steel rebar. 

 
										 
										 
										 
										 
										 
										 
										